|
Hot
Weather Masonry Construction
Limiting your Exposure
Introduction
Those who design with masonry
appreciate its appearance, durability, flexibility,
and rapid rate of construction. We also know it as
a construction material whose final product is
dependent upon the quality of its individual
components and the care and craftsmanship taken to
assemble them. Under normal working conditions
this care is often challenged by the unique shapes
and congested reinforcing cells that must be
accommodated. When environmental conditions become
extreme, maintaining good quality becomes
increasingly difficult.
This article addresses one
particular environmental factor that rarely gets
much attention - hot weather. It will explore the
effects that hot weather construction can have on
the overall quality of masonry construction and to
recommend some provisions to help mitigate poor
results. Included are some suggestions taken
directly from ACI 530.1-02/ASCE 6-02/TMS 602-02
"Specification for Masonry Structures". These same
provisions are also included as part of the 2001
IBC. Also included, are a number of suggestions
for items such as pre-construction meetings and
required submittals that specifically address the
safeguards to be taken when hot weather conditions
exist. The intent is to get everybody thinking
about the possibility of encountering these
conditions and having plans ready to execute in
case they do occur.
Signs of Hot Weather
Most of the challenges
associated with hot weather masonry construction
are similar to those of concrete and relate to an
increased rate of hydration and an increased rate
of evaporation of the grout and/or mortar. Where
proper provisions are not implemented, the
following undesirable affects could be encountered
during construction:
· Decreased
28-day strength.
· Decreased
workability and increased rate of
stiffening
· Excessive
shrinkage and poor bonding of grout to concrete
masonry units
· Moisture
kiss
Poor quality of masonry
construction during hot weather can also be
exacerbated by several other common practices that
should be considered in conjunction with any
special procedures that may be developed. These
items include:
· High lift
versus low lift grouting techniques and
consolidation
· High slump
grout mix and pumping
· Use of
admixtures
Each of these items is
discussed below in more detail within the following
sections.
Curing and 28-Day
Strength
During periods of hot
weather, the ultimate design strength of both
mortar and grout can be compromised. This
reduction in strength is generally due to both the
increased ambient temperature and/or low humidity,
and to the additional water that must often be
added to achieve the same workability. High curing
temperatures, for example, tend to promote higher
initial strengths (1-Day), but ultimately lead to a
reduced 28-Day Strength. This relationship is
illustrated in figure 1 below. Note that an
increase in ambient air temperature of roughly
65°F will cause a strength decrease of
approximately 30%. Low or even decreasing relative
humidity, a factor often associated with high
temperatures, will likely promote further strength
reductions. Since grout and mortar are both
cement-based materials of similar composition to
concrete, the same conclusion could be drawn for
these materials.

Figure 1
Effects of Curing Temperature on Concrete
Strength
Workability &
Stiffening
Aside from curing
temperature, the amount of water in a mix is the
other factor that will significantly influence
ultimate design strength. During hot weather
conditions, water is often added to grout and
mortar at the jobsite to maintain effective pumping
and workability. This need for increased water is
caused by higher rates of water evaporation and
higher initial mix temperatures. Unless more
cementitious materials are added, or a portion of
the mix water was initially left out at the batch
plant, the resulting grout and mortar will most
likely exhibit decreased strength and durability.
Aggregate or cement that is left out in the sun,
for example, will retain considerable heat and lead
to higher mix temperatures. This higher initial
mixing temperature will subsequently require more
water to maintain the same slump. Figure 2
indicates that a 1-inch difference of slump can be
expected for each 20° F change in concrete
temperature. This figure also illustrates that at
60°F, it takes approximately 2.25% more water
to increase the slump 1". Where concrete
temperature has reached 125° F, the same 1"
increase in slump would require approximately
4½% more water. This is obviously a
non-linear relationship with progressively far more
water required at higher mix temperatures.
Once mixed, the usable life
for both mortar and grout are obviously limited.
This shelf life is largely dependent upon mix
consistency, temperature during set, and the rate
of water loss caused by evaporation or absorption
to the adjacent block.
Although the reaction between
cement and water are very complex, one can
generally assume that the reaction rate or
stiffening will double for each increase of
20°F in mix temperature. Most codes allow for
a one-time re-tempering of mortar with water to
maintain workability, but state that mortar must be
discarded 2 ½ hours after initial mixing.
Grout, by contrast, generally has enough water so
set time is not generally as critical. Even so,
care must be taken to limit grout placement such
that re-consolidation between successive lifts can
be conducted within one hour of placement.

Figure 2
Effects of Temperature on Water
Requirements

Figure 3
Effects of Concrete Temperature on Slump &
Water
Excessive Shrinkage and
Poor Bonding
Construction of concrete
masonry generally requires high slump grout mixes
and small aggregates that can be easily pumped into
congested spaces. Under normal environmental
conditions, mixes with such a significant amount of
water and high fine-aggregate contents will
experience considerable plastic and drying
shrinkage that must be considered. This problem is
often exacerbated during hot weather as water
requirements increase without design mix
modifications.
Plastic shrinkage, or the
loss of volume during initial setting, occurs when
the rate of evaporation exceeds the rate of bleed
water migrating to the surface or when mixing water
is rapidly drawn out of the mix by contact with the
block. For both mortar and grout, this rapid water
loss can lead to unsightly cracks, poor bonding,
and on occasion, a cement paste that is
under-hydrated. Proper consolidation and
especially reconsolidation after excess moisture
has been absorbed, but before plasticity is lost,
is the first line of defense against this problem.
Improved mix designs that incorporate water
reducing, retarding, and expansive agents1 are
another item that may be considered.
Drying shrinkage, in
contrast, occurs after grout or mortar has set and
is caused by the continued loss of water over
years. This shrinkage is largely dependent upon
the original content of water within the mix, the
proportion and properties of coarse and fine
aggregate, and the curing conditions. An increase
in mixing water of 1%, for instance, will generally
produce a 2% increase in shrinkage. Soft aggregate
or those that absorb considerable moisture are also
more prone to drying shrinkage.
CMU and Moisture
Kiss:
The use of concrete masonry
units is advantageous as it permits intricate work
in tight conditions and eliminates the use of
additional wood or steel forms.
During periods of hot
weather, however, special attention should be given
to these blocks as they can significantly influence
the characteristics of the grout mix as placed.
Blocks that are excessively hot or dry, for
instance, can cause rapid moisture loss in the
grout and significant plastic shrinkage as
described above. This rapid loss of mix water,
which is labeled "moisture kiss," can even rob
mortar of the water required to fully hydrate and
exacerbate the ability of the grout to properly
bond to the inside face of block. Similar to grout,
mortar can also experience a rapid moisture loss
where blocks are excessively hot and dry leaving
mortar partially un-hydrated and with decreasing
strength. Exposed surfaces of these joints are
particularly susceptible since they are also
subject to a higher rate of evaporation. This may
leave the finished mortar joint sandy or chalky to
the touch with reduced strength and durability.
Suggested Guidelines for
Hot Weather
Poor results due to hot
weather conditions can be linked to high ambient
air temperature, low relative humidity, wind speed
or any combination of these factors. To be
effective any triggers linked to these factors must
be practical, easily distinguished and applied to
each sequence in the construction process. To this
end, the Masonry Standards Joint Committee (MSJC)
has established special provisions that must be
followed whenever hot weather conditions exist.
These guidelines are shown in matrix form in
table's 1a, 1b, and 1c below and are divided up
into requirements during preparation of the masonry
work (prior to construction), during construction
(work in progress), and for protection (after
masonry elements are constructed). These
guidelines are followed by some additional
suggestions that can be either incorporated into
design specifications, or discussed at
pre-constructions meetings as appropriate.
|
Condition
|
Requirement
|
|
Ambient Temperature
exceeds 100°F or exceeds 90° F,
with a with a wind velocity greater than 8
mph.
|
|
1.
|
Maintain
sand piles in a cool loose
condition.
|
|
2.
|
Provide
necessary conditions and
equipment to produce mortar
having a temperature below
120°F2
|
|
|
Ambient Temperature
exceeds 115°F or exceeds 105°F,
with a with a wind velocity greater than 8
mph.
|
In addition to the
requirements above, provide the
following:
Maintain sand piles in a damp loose
condition
|
Table 1a: Preparation (Prior to conducting
masonry work)
1Admixtures,
especially those containing water reducers, should
be tested with a particular mix well in advance of
use to ensure good performance and compatibility
with the remaining mix components.
2 Most
building codes limit concrete temperature at time
of placement to 90°F.
|
Condition
|
Requirement
|
|
Ambient Temperature
exceeds 100°F or exceeds 90°F,
with a with a wind velocity greater than 8
mph.
|
|
1.
|
Maintain
temperature of mortar and grout
below 120°F
|
|
2.
|
Flush
mixer, mortar transport
container, and mortar boards with
cool water before they come into
contact with mortar ingredients
or mortar.
|
|
3.
|
Maintain
mortar consistency by
re-tempering with cool
water.
|
|
4.
|
Use mortar
within 2 hours of initial
mixing.
|
|
|
Ambient Temperature
exceeds 115°F or exceeds 105°F,
with a with a wind velocity greater than 8
mph.
|
In addition to the
requirements above, provide the
following:
|
1.
|
Use cool
mixing water for mortar and
grout. Ice is permitted in
mixing water prior to use. Do
not permit ice in mixing water
when added to other mortar and
grout.
|
|
Table 1b: Construction (While masonry work is
in progress)
|
Condition
|
Requirement
|
|
Ambient Temperature
exceeds 100°F or exceeds 90°F,
with a with a wind velocity greater than 8
mph.
|
|
1.
|
Fog spray
all new completed masonry work
until damp at least three (3)
times a day until masonry work is
three (3) days old.
|
|
Table 1c: Protection (While masonry work is
curing)
Additional
Considerations
Testing Mortar and Grout
Temperature: As discussed above, the temperature
of mortar and grout at placement has a significant
effect on the final strength development and extent
of shrinkage that will result. As noted in Table
1, the MSJC recommends keeping temperature of both
of these constituents below 120°F to limit
detrimental effects. In general, grout mixes
rarely exceed 90°F as delivered to the job
site due to the large quantity of water within a
typical grout mix. In the author's opinion,
90°F may be more appropriate to provide
consistency with concrete codes. These
temperatures should be taken at the point of hose
discharge or at the smaller mortar piles where
block is being constructed.
Long black hoses exposed to
the sun can significantly alter the grout
temperature as placed. To help alleviate this
problem, hoses should be shaded and flushed with
cold water whenever possible. Wetting down the
hoses with cold water at regular intervals is
another option that can help reduce temperatures.
Proper Consolidation:
Ensuring proper consolidation for grout is perhaps
the most important safeguard that can be put in
place under any weather conditions. Grout must be
initially consolidated to ensure complete filling
of voids, and then reconsolidated after excess
moisture has been absorbed but before plasticity is
lost. The timing for this second consolidation is
critical for success and takes experienced workers
and ample manpower. Under extreme conditions and
where cells are congested, low-lift grouting may be
more appropriate than high-lift grouting
techniques. The reader is referred to the CMACN
for procedures on high-lift versus low-lift
grouting procedures.
Admixtures:
Water-reducing or water-reducing and retarding
admixtures can help improve workability by slowing
down the initial rate of hydration and the
stiffening process, as well as increasing the
workability by decreasing the water demand. Some
admixtures also contain components, which provide
an expansive action that helps counteract shrinkage
due to volume loss. All admixtures should be
properly tested or have sufficient data to verify
compatibility with the mix design prior to use.
Aggregate: Initial
aggregate temperature will generally have the
greatest affect on the initial temperature of the
mix. This is due to the high relative mass and
specific weight as compared to the other
components. As mentioned above, aggregate supplies
should be kept shaded or occasionally sprayed down
to keep temperatures as low as practical. Where
water is used to wet down the aggregate, care
should also be taken to ensure consistent overall
water cement ratios of the grout mix.
Use of Fly ash: Many
suppliers recommend adding up to 15% fly ash to
grout mixtures to help control the unsightly
affects of efflorescence. Under the right
conditions, fly ash can also help improve
workability, slightly retard setting time, and
increase 28-day design strength, as well as
ultimate strength at later ages. Similar to
admixtures, any mixes incorporating fly ash should
be substantiated by previous testing data or be
tested by trial batches to ensure proper results
are achieved.
Water: Control of
water quantities and temperatures are essential
during hot weather. Reducing the temperature of
water has been shown to be one of the most
effective methods for controlling mix temperatures
as placed. Water has a specific heat of
approximately 4 to 5 times that of cement or
aggregate and as such has the greatest effect per
unit weight on initial mix temperature. Careful
consideration should be given to initial water
temperatures at the batch plant, as well as any
water added on site to the grout. Maintaining cool
mixing water at the site for both mortar and grout
may be best accomplished with ice although any ice
must be completely melted before mixing.
Alternate Grout Mix
Designs: Alternate grout mix submittal may be
advantageous during hot weather conditions. Such
mix designs should be substantiated by previous
test data or tested well in advance.
Preplanning: Last
minute adjustments made to address hot weather
conditions are rarely effective. Preplanning
should start well before construction operations
begin and be accompanied with specific procedures
that are reasonable and understood by all parties.
Decisions whether or not to implement these
procedures should be made at least the day before
construction begins and can be easily tied to local
weather forecasts.
Employee Concerns:
Working with masonry is physically demanding enough
without soaring temperatures. Working in these
conditions without additional precautions can lead
to decreased productivity and care in quality, and
increased injury and illness. Although there is
little that a practicing engineer can do to dictate
when, where, and for the most part how the work
will be carried out, at least mentioning such items
during the pre-construction couldn't hurt. Some
suggestions that may be made include:
|
·
|
Gradually adapting
workers to the more strenuous
tasks
|
|
·
|
Preplanning work to
and ensuring estimated daily goals are
reasonable under the more
difficult conditions.
|
|
·
|
Postponing the most
difficult tasks to cooler mornings or late
evenings
|
Previous Test Reports:
Grout is generally specified by proportion of
volume or by minimum compressive strength. Where
previous test reports are available, review of
dates and listed temperatures may provide a rough
guide to anticipate how the mix may perform during
hot weather. Specifications could require any
previous test data categorized this way. You may
also want to verify that the original mix design
and corresponding water-cement ratio was
proportioned for hot-weather conditions.
References:
|
1.
|
Building Code
Requirement for Masonry Structures
ACI 530-02/ASCE 5-02/TMS 402-02
|
|
2.
|
2001 California
Building Code, Volume 2
|
|
3.
|
2003 International
Building Code
|
|
4.
|
ACI Manual of
Standard Practice 2004, Part 2 ACI 305R-99
Hot Weather Concreting
|
|
5.
|
Specification for
Masonry Structures
ACI 530.1-02/ASCE 6-02/TMS
602-0
|
This issue of "Masonry
Chronicles" was written by Colin Blaney S.E.,
Principal with the Crosby Group, Redwood City,
California.
|